|  (Last Updated: 23-AUG-10)
|
 |
KEY ACHIEVEMENTS SO FAR - August 2007 | General issues | - The Stakeholder Group met in April and provided an update on the work of the IGs and on the agreed Action Plan.
- At present, focus has been on evaluating the impact of the start of the Estlink operation. This exercise has produced practical proposals on how to avoid pan-caking of payments.
- A working paper on licensing issues has also been produced and no major barriers to entry were identified.
| Priority I Cooperation between network operators (including cross border issues and availability of transmission capacity). | - Work on ITC issues towards the delivery of a Working Paper stating the Baltic TSOs opinion on the ETSO ITC mechanism is ongoing.
- The region is currently investigating solutions to pancaking regarding payments for transferring the energy to Estlink. A meeting is planned with Finnish TSO representative.
| Priority II Access to grids and balancing rules | - The IG on balancing issues will further develop draft Working Paper on Balancing in the Baltics (the first draft has already been prepared).
- Producers came up with the proposal to include in the further actions the problems of market design and fair transmission pricing.
| Priority III Availability and control of information | · The NRAs agreed on using the ERGEG Transparency Guidelines for Good Practice as the key template for assessing transparency across the Baltic region. | Priority IV Market development and compatibility with national legislation | · The IG on Licensing issues produced a summary paper on the license issuing procedures in the Baltics. |
|
 |